Remediation with ERD Injection – Brindisi
Project Goals and Outcomes
Client: Aeronautical and aerospace company
Location: Brindisi production site
Client Goal: Reduce chlorinated solvent and Chromium [Cr(VI) and total] contamination in groundwater by organic substrate injection.
Our Role: Design and implementation of an ERD (Enhanced Reductive Dechlorination) plant with organic substrate injection in 14 wells.
Result: Chlorinated solvent concentrations lowered below risk targets approved by regulatory agencies; progressive reduction of heavy metals; full regulatory compliance.
Performance of the Plant
14 wells
Totals per substrate injection
1,5-2 m3/g.
Flow rate mixture water + organic substrate
ERD
Applied technology (reductive biodegradation stimulation)
The GEOSTREAM Solution
Injection plant for controlled mixing and distribution of organic substrate (whey) and water, designed to feed the 14 wells located on the contaminated area.
Complete system of: storage unit, mixing, injection station, hydraulic lines and parameter control instrumentation.